Project

4D Scheduling

Client

Ontario Power Generators

Technologies

VR, Unity

This system connects to the nuclear power plant's work-planning and scheduling database. It uses a combination of 3D scanned environments and CAD files to recreate work locations and gives the user an option to move time forwards and backwards, visualizing the work progress. This allows the work manager to detect conflicts in resources and space ahead of time. In this particular example, it was discovered that the crane would need to be assembled inside the room, as it doesn't fit through the door.